Risk or issue?

There seems to be much confusion between the two but it’s really simple so I will try to shed some light on this topic.

A risk is a specific event that may happen. If it does, it will affect your project negatively or positively , so you want to prepare in order to make sure your project goes well.

An issue is something that must be dealt with. A risk, wether identified or not, becomes an issue.

Here are some examples:
Risk: There may be too many users visiting the website, and the server may not handle it.
Issue: Too many users visit the website and the server crashed, we have to add resources.

I hope this helps!


1 Comment

Risks: not always negative

A common thinking about risks is that they are all negative and should be mitigated or avoided as much as possible. That common thinking is wrong!

A negative risk is a treat, but a risk can be positive and considered an opportunity so instead of mitigating or avoiding, you’ll want to exploit or enhance.

A good example is the risk of having too many visitors on your brand new website on the day of the launch. Having lots of visits is positive, so it’s not a treat unless it’s poorly planned and can crash the server, so you have to take it into consideration.

You may want to enhance the risk (plan a marketing blast to attract even more visitors) or exploit (use cloud hosting that can adapt resource accordingly, or have more resources ready for the server so you can welcome more visitors). You could simply accept and make sure the website simply displays a temporary message if too many people are visiting at once.

Risks are not all that bad, and even positive ones shouldn’t be ignored.